Update Project
UiPath.Jira.Activities.UpdateProject
The Update Project activity uses the Jira API to update a project (Project).
After updating the project, the activity outputs another project object (Updated Project). This can be used as an input variable in subsequent activities (e.g., Project in Delete Project in conditional logic.
How it works
The following steps and message sequence diagram is an example of how the activity works from design time (i.e., the activity dependencies and input/output properties) to run time.
- Complete the Setup steps.
- Add the Jira Scope activity to your project.
- Add the Update Project activity inside the Jira Scope activity.
- Create and enter a
Projectand aProjectvariable for the input properties. - Create and enter a
Projectand aUpdated Projectvariable for the output properties.
Properties
Common
- Continue On Error - This field only supports boolean values (True, False). The default value in this field is False. As a result, if this field is blank and an error is thrown, the execution of the project stops. If the value is set to True, the execution of the project continues regardless of any error.
- DisplayName - The display name of the activity. This field supports only strings or
Stringvariables.
Input
- Project - The project to update. Enter a
ProjectorProjectvariable.
Misc
- Private - If selected, the values of variables and arguments are no longer logged at Verbose level.
Output
- Updated Project - The updated project. This field supports only
Projectvariables. The variable you create for this property can be used as an input variable in subsequent activities (e.g., Delete Project, etc.).